BEDC hinges signing of Ossiomo contract agreement on regards for safety, public costs

The Management of BEDC Electricity Plc (BEDC) has explained that the delay in signing the bilateral agreement on the Edo State and  Ossiomo Power project was due to Ossiomo’s non agreement to the process for the operations, maintenance and management of the line being constructed in line with licensing and safety standard in order to ensure safety of lives and property.

Also, the procurement process for the proposed new line, expected to be based on open & competitive procurement inline with prudency requirement by the regulators has not been agreed to by Ossiomo.

When combined with the proposal by Ossiomo that the valuation methodology for the pricing of purchase in 10years time should be agreed to in future, BEDC has stated that these can lead to tariff costs that may not conform to regulatory approval. BEDC has thus requested for the release of the draft agreement for its review and clearance by the regulator.

Making BEDC’s position known was the Chief State Head, Edo State of BEDC, Mr. Abel Enechaziam during a Media Parley organized by the company on Friday in Benin.

“As you are aware, we operate in a regulated sector and would require the sign off of the relevant sector regulators such as NERC  before executing the proposed agreement, in order to ensure that we remain within the permitted regulatory parameters” , BEDC declared.

It pointed out that one of the two grey areas that were in contention in the bilateral agreement on Ossiomo bordered on the need for valuation of the line being used for power evacuation through open, competitive and transparency tendering process to ensure that only prudent cost are passed to the customers.

The other issue of dispute, the company explained further was its insistence that joint operation and maintenance of the Ossiomo line was not allowed and that a sub contactor could be appointed by Ossiomo to work under BEDC supervision for accountability and safety sake in its network.

“The recent electrocution of two persons occasioned by Ossiomo’s ongoing construction which interfaced with our distribution line thereby causing supply interruption to the community in the area as well as  death of one of the parties involved, indeed emphasizes the need for the project to be undertaken in line with applicable regulatory and safety standards.” BEDC said.

The company affirmed that it was ready to partner with Edo state government on the Ossiomo power project as evidenced by its constant efforts at ensuring that the Nigerian Electricity Regulatory Commission (NERC) clearance letter is properly and safely implemented.

Addressing the media on the activities of BEDC, Mr. Enechaziam said that power supply in GRA, Ugbowo, Sapele road in Benin City and also Auchi Okada, Uromi, Ekpoma all in Edo state is presently fairly stabilized and improved due to network maintenance and upkeep.

“BEDC commissioned a 1×7.5MVA Uteh injection substation which has improved the supply to Uteh community and Upper mission axis. The existing 33KV Koko line from Benin transmission office was extended in Evbuoriaria, Evbuabogun and Ologbo communities and environs for improvement in power supply condition,” he added.

Speaking on the Meter Asset Provider (MAP) scheme introduced by NERC to close the metering gap of customers all over the country, Enechaziam said BEDC has introduced the Neighborhood Saturday Fast Track metering scheme for its customers who were ready to pay MAP fully for the cost of meter; stressing that the process is now subsumed under a three tier process.

He listed three methods being used by BEDC and MAP to accelerate metering to include 1. Saturday fast Track for meter installation for full payment, 2.Business Unit continuous Daily comprehensive registration and 3. Door to Door metering based on transformer by transformer, adding” under the Saturday Neighbourhood fast track metering, BEDC provides a one-stop service to customers including customer complaints resolution, enumeration, premise inspection, payment and metering installation with a view to quicken the process,”

In line with request by NERC to Distribution Companies (Discos) to transit to cashless platform for industrial and commercial customers before March, BEDC he said, has developed a robust payment option channels for its customers among which he disclosed, was the deployment of 1,017 POS terminals and collection agents to strategic locations in the coverage states.

Enechaziam also disclosed that in furtherance of its mandate of ensuring power availability in communities without power supply for a long time or yet to be connected to the national grid BEDC has connected over 48 communities to the grid as at October 2019, with 16 of such connections done in Edo state.

 




Leave a Reply